India Datacenter WeeklyIssue 2Week to 5 October 2026

A gigawatt in Odisha, and what the per-MW numbers show

Odisha clears 1.24 GW in one round. The Jewar 400 kV node is late. Open access costs reset in four states.

AISIGINT Research

Odisha clears 1.24 GW in one round

On 23 September the state's high-level clearance authority approved three datacenter projects: Adani at 1 GW in Naraj, HCLTech with Sarvam in Khordha (120 MW, scaling to 300 MW), and Sentraforge AI at 120 MW in Puri. Together that is 1.24 GW and about ₹1.41 lakh crore of stated investment.

For scale: Mumbai, the largest datacenter market in the country, runs 890 MW today. The top seven markets together run 1,789 MW, with vacancy at 14.9% (Cushman and Wakefield, H1 2026). A single site in Odisha has been cleared for more capacity than Mumbai has built.

Adani, Naraj
Stated investment
₹1,04,550 crore
Stated capacity
1,000 MW
Investment per MW
About ₹105 crore
HCLTech with Sarvam, Khordha
Stated investment
₹14,257 crore
Stated capacity
300 MW at full scale
Investment per MW
About ₹48 crore
Sentraforge AI, Puri
Stated investment
₹22,634 crore
Stated capacity
120 MW
Investment per MW
About ₹189 crore

The east coast is filling in beyond Odisha. Andhra Pradesh's project list now carries a 512 MW AI factory at Bheemunipatnam and a 100 MW campus at Rambilli, and the I-2SEA subsea cable is due to land at Machilipatnam and South Chennai in 2029. Capacity, land and cable are moving to the same coastline.

Uttar Pradesh: Jewar is late

The 400/220 kV Jewar substation (2x500 MVA), which serves the airport belt, has asked the state regulator, UPERC, to extend its commissioning date. It had an 18-month build clock from March 2024. The hearing is on 17 November. The next 400 kV node, Sector-28 in the Yamuna Expressway authority (YEIDA) area (3x500 MVA, ₹629 crore), goes to bid on 2 November and sits in the state plan for FY 2028-29. The plan itself is large: ₹38,520 crore and 137 new substations over five years.

The UP Data Centre Policy 2026 has been in force since 9 July. It gives ten years of electricity duty exemption, 25 years of transmission and wheeling relief at 50-100%, dual-grid cost reimbursement and two-feeder supply. The transmission and wheeling relief is capped at the first eight parks or an extra 2 GW.

Telangana: large commitments, record demand

TCS HyperVault has acquired 264 acres in Hyderabad for a campus of up to 1 GW. Two more blocks of 170 and 10 acres are on record in the same Future City belt. Microsoft formally opened its Hyderabad cloud region on 24 September.

Statewide peak demand hit a record 19,892 MW on 30 September, passing the 19,543 MW set on 9 September, and the Hyderabad distribution company (discom) set its own record of 12,299 MW. The discom is developing dual-source supply for datacenters and has named the Thimmapur-Kandukur corridor. The state generator is tendering a 187.5 MW / 750 MWh battery at Maheswaram, the nearest 400 kV node (bids 23 October).

Open access cost, October 2026 to March 2027

Gujarat
Additional surcharge
₹0.99 per kWh (up from ₹0.76, about 30%)
Tamil Nadu
Additional surcharge
₹0.63 per kWh
Status
Discom petition, not yet ordered
Karnataka
Additional surcharge
₹0.40 per kWh
Status
Interim rate continues
Telangana
Additional surcharge
Previous ₹0.13 lapsed on 30 September
Status
No new order found

Tamil Nadu's regulator had no quorum from 2 June until it was reconstituted on 18 September. The FY 2026-27 tariff order is more than three months overdue and the state datacenter policy has lapsed. Chennai has 214 MW operational and is running without a current tariff order or a current policy.

In Maharashtra, the state regulator MERC has seven draft rules out and comments close on 12 October. In-kind banking would end. A working estimate from the drafts, not a figure the regulator has published, is a fixed banking and standby charge of about ₹139 per kW per month, plus ₹3-4 per unit variable (tentative). Green open access would start from 100 kW, and new behind-the-meter systems above 100 kW would carry a storage obligation. Separately, the state has widened its green datacenter park scheme to 20 parks, cut the green energy floor to 51% and offered ₹1 per unit off the tariff.

Gujarat and Karnataka

Gujarat told its Assembly it holds about 17 GW of datacenter expressions of interest from 17 parties against a 7.5 GW target. Grid tenders are moving more slowly: the Dholera-II 400 kV package was due to close on 7 October after a 47-day slip, and two STATCOM packages are on their third extension.

Karnataka's incentives were reported in the press for the first time, including up to ₹20 crore for PUE of 1.20 or better. The government order is not yet out. The regulator granted the state's first two private 400 kV transmission licences, and the Kadandale 400/220 kV substation is complete.

Slip watch

Jewar 400/220 kV substation
State
Uttar Pradesh
Was due
September 2025
Now
Extension sought; hearing 17 November
Slip
Over 12 months
Dholera-II 400 kV substation tender
State
Gujarat
Was due
Close on 21 August
Now
Close on 7 October
Slip
47 days
Two STATCOM packages
State
Gujarat
Was due
Not published
Now
Not published (third extension)
Slip
Not published

Net read

A strong week for announcements and a slow one for the grid behind them.

  • What looks solid: demand, the arrival of the east coast as a datacenter region, and state policy that improves with each round.
  • What to discount: headline investment figures, any date that depends on a 400 kV substation not yet awarded, and any open access model built before this winter's orders.

Dates ahead

12 October
MERC draft comments close
Maharashtra
16 October
UPERC parallel licence hearing
Uttar Pradesh
21 October
Ekarajapura 220 kV bids close, Hosakote
Karnataka
23 October
Maheswaram battery bids due
Telangana
2 November
YEIDA Sector-28 400 kV bids due
Uttar Pradesh
17 November
UPERC hearing on Jewar
Uttar Pradesh

AISIGINT tracks grid, regulation, land and operator moves across Indian datacenter markets, and uses that evidence in site-level power and delivery assessments. This note is general market information, not advice on a specific site or transaction. Corrections and additions are welcome at info@aisigint.com.

Get the next issue

One email a week on Indian datacenter markets.

Grid, power cost, policy and new capacity, with facts and judgement kept apart.

All past issues →

Free. One email a week. We send a confirmation link first, and every issue has an unsubscribe link. See the privacy policy.