India Datacenter WeeklyIssue 4Week to 19 October 2026

India's policy think tank advises states to sanction datacenter load only after supply works are commissioned

A 765/400 kV substation award adds bulk supply for Pune west. Tamil Nadu paid up to ₹37 per unit for emergency evening power. The licensee for Greater Noida's new datacenter park reports 200 MW of expected load.

AISIGINT Research

National: grid first, then datacenter load

The government policy think tank, NITI Aayog, released its datacenter evaluation framework for states on 14 October. It has five pillars. A load sanction comes only after the supply infrastructure is commissioned. Facilities above 20 MW take part in demand response. Renewable supply is matched hourly. Water red zones are marked. The electronics and IT ministry, MeitY, is the nodal audit ministry. The framework is advisory and binds no state.

For power, the framework asks for a jointly validated power ramp-up plan from the developer, the distribution company (discom) and the state transmission utility: sanctioned MW, year-wise energisation, substation upgrades and their lead times. It also asks for substation load flow studies and a published power infrastructure roadmap. No state has reported adopting it.

Separately, the Minister of State for Electronics and IT, Jitin Prasada, said on 14 October that the government is preparing a datacenter policy so that the sector's power demand does not raise household electricity bills. No text, provisions or timeline are published. Reports of the statement cite a Ministry of Power estimate of 26.3 GW of AI datacenter load by 2031-32.

Maharashtra: Pune West 765/400 kV awarded

POWERGRID received the Letter of Intent for the Pune West 765/400 kV GIS substation on 16 October, at annual transmission charges of ₹199.55 crore. The scheme has 2x1,500 MVA of transformation, a 400 kV double circuit line to the Hinjewadi 400 kV substation of the state transmission company, MSETCL, and a loop-in of the 765 kV Pune-III to South Kalamb line. It is a build, own, operate and transfer project, due 24 months from transfer of the project company. The transfer date is not published.

It is the second new bulk supply scheme for the Pune west datacenter cluster, after the Jejuri to Hinjewadi line.

The state government has formed a high-level committee led by Anil Kakodkar on the environmental, water and infrastructure impact of datacenters. Members include the state discom MSEDCL, MSETCL, the industrial corporation MIDC, NEERI and IIT Bombay. A datacenter standard operating procedure and a report are due within three months.

Tamil Nadu: emergency power at up to ₹37 per unit

The outcome of the 12-31 October emergency tender is now known. The Tamil Nadu distribution company, TNPDCL, contracted 2,062 MW early morning at ₹31.99-34.49 per unit and 2,001 MW evening at ₹33.37-37 per unit. Evening peak reached 20,527 MW on 12 October. Central station supply was short by nearly 4,000 MW for maintenance, and wind gave about 500 MW against 3,500 MW contracted.

After the northeast monsoon set in, demand fell about 1,000 MW and short-term purchases were cut to under 300 MW.

The Tamil Nadu regulator, TNERC, extended the comment deadline on nine draft regulations from 15 October to 31 October. They include the distribution multi-year tariff, battery storage, intra-state transmission tariff and deviation settlement regulations.

CapitaLand unveiled Chennai 01 at Ambattur, Chennai: 34 MW IT and 53 MW gross, 13 halls, a dedicated 110 kV substation and about ₹1,940 crore, with completion by end-2026. It is under construction, not operating.

Grid and storage: Gujarat, Karnataka, Odisha and the south

The Gujarat regulator, GERC, finalised its Grid Interactive Battery Energy Storage System Regulations, 2026 on 16 October, closing a draft open since 12 May. They cover standalone storage above 1 MW with at least two hours, at 11 kV or above. A co-located battery charges only from its renewable plant. Grid charging without matching contract demand attracts the temporary supply tariff. The notification number and gazette date are not stated.

GERC also posted draft amendments to the Supply Code and to the discom Standards of Performance Regulations, which set the procedure and time limits for new high-voltage connections. The comment deadline is not yet known.

The Karnataka regulator, KERC, issued a public notice on the Ryapte Power Transmission licence petition for the Ryapte 5x500 MVA and Doddathaggalli 3x500 MVA GIS substations near Hosakote, east of Bengaluru. The licence is not yet granted.

The Odisha transmission company, OPTCL, tendered a 220 kV double circuit underground cable from the 400 kV Mendhasal substation to the 220/33 kV Infocity-II substation in Bhubaneswar, with two 220 kV GIS bays at each end. The estimate is ₹168.91 crore and bids close 16 November. It adds 220 kV supply to the Infocity and Chandrasekharpur datacenter cluster.

New capacity

The Uttar Pradesh regulator, UPERC, recorded the first licensee-reported load for Greater Noida's new integrated datacenter park in an order of 14 October: 200 MW total expected load, 8.5 MW existing, 12 MW expected by February 2027 and 20 MW in 2028. UPERC approved bagasse-based round-the-clock power at ₹5.12 per unit (5 MW, November 2026 to March 2027) and ₹5.10 per unit (3 MW, January to March 2027).

Colt DCS and RMZ started construction of Mumbai 3 at their Navi Mumbai campus, 64 MW of contracted power, fully pre-let to a hyperscale customer. The campus reaches 86 MW on completion and up to 148 MW.

Slip watch

The four Gujarat transmission company tenders below reached their extended closes on 14-17 October; no outcome or award is published. In Karnataka, the Kadakola tender close also moved from 7 October to 21 October.

Jewar 400/220 kV substation
State
Uttar Pradesh
Was due
September 2025
Now
Extension sought; hearing 17 November
Slip
Over 12 months
Dholera-II 400 kV GIS substation tender
State
Gujarat
Was due
Close on 21 August
Now
Close on 14 October; outcome not published
Slip
54 days
Sagapara 220 kV STATCOM tender
State
Gujarat
Was due
Close on 7 September
Now
Close on 16 October; outcome not published
Slip
39 days
Godadara 220 kV GIS substation tender
State
Gujarat
Was due
Close on 8 September
Now
Close on 14 October; outcome not published
Slip
36 days
Tharad 220 kV STATCOM tender
State
Gujarat
Was due
Close on 17 September
Now
Close on 17 October; outcome not published
Slip
30 days
Hootagalli 220 kV augmentation tender
State
Karnataka
Was due
Close on 7 October
Now
Close on 21 October
Slip
14 days

Open access cost, October 2026 to March 2027

No state ordered a new rate this week. In Telangana, the regulator's orders page still lists the first-half order at ₹0.13 per kWh as the latest, nineteen days into the second half.

Gujarat
Additional surcharge
₹0.99 per kWh
Status
Ordered by GERC
Tamil Nadu
Additional surcharge
₹0.63 per kWh
Status
Discom petition, not yet ordered
Karnataka
Additional surcharge
₹0.40 per kWh
Status
Interim rate continues
Telangana
Additional surcharge
Not published
Status
Lapsed, no new order found

Capacity and grid

Tamil Nadu
Not yet operating
21,092 MW
Connection substation named
0 MW
Projects
11 (3 with no MW published)
Maharashtra
Not yet operating
10,544 MW
Connection substation named
2,500 MW
Projects
29 (9 with no MW published)
Andhra Pradesh
Not yet operating
7,698 MW
Connection substation named
0 MW
Projects
13 (2 with no MW published)
Telangana
Not yet operating
6,607 MW
Connection substation named
612 MW
Projects
18 (5 with no MW published)
Madhya Pradesh
Not yet operating
1,892 MW
Connection substation named
0 MW
Projects
8 (3 with no MW published)
Odisha
Not yet operating
1,175 MW
Connection substation named
0 MW
Projects
9 (5 with no MW published)
Uttar Pradesh
Not yet operating
946 MW
Connection substation named
150 MW
Projects
10 (3 with no MW published)
Karnataka
Not yet operating
635 MW
Connection substation named
0 MW
Projects
8 (5 with no MW published)
Gujarat
Not yet operating
588 MW
Connection substation named
0 MW
Projects
7 (3 with no MW published)
West Bengal
Not yet operating
295 MW
Connection substation named
0 MW
Projects
8 (5 with no MW published)
Chhattisgarh
Not yet operating
280 MW
Connection substation named
0 MW
Projects
4 (1 with no MW published)
Haryana
Not yet operating
200 MW
Connection substation named
0 MW
Projects
2 (1 with no MW published)
Bihar
Not yet operating
150 MW
Connection substation named
0 MW
Projects
1
Delhi
Not yet operating
0 MW
Connection substation named
0 MW
Projects
1 (1 with no MW published)
Kerala
Not yet operating
0 MW
Connection substation named
0 MW
Projects
1 (1 with no MW published)
Punjab
Not yet operating
0 MW
Connection substation named
0 MW
Projects
2 (2 with no MW published)
Rajasthan
Not yet operating
0 MW
Connection substation named
0 MW
Projects
2 (2 with no MW published)

A substation counts as named only when a utility or regulatory document names it, and naming is not a promise of power.

Net read

The week's firm steps were grid and regulatory: a 765/400 kV award for Pune west, final battery rules in Gujarat and a 220 kV cable tender in Bhubaneswar, while new capacity came mostly as Letter of Intent and MoU megawatts.

  • What looks solid: the Pune West Letter of Intent, the GERC battery regulations, the OPTCL Mendhasal to Infocity-II tender and the UPERC record of 20 MW by 2028 for the Greater Noida park.
  • What to discount: Letter of Intent and MoU megawatts such as Bodh Gaya and Haryana, which carry no connection filing, and the Gujarat tender dates until an award is published.

Dates ahead

21 October
KPTCL tenders close for the Hootagalli, Kadakola, Ekarajapura and Begur works and the Bannerghatta Road package
Karnataka
23 October
Bids due for the Maheswaram 187.5 MW / 750 MWh battery storage re-tender
Telangana
26 October
MERC comments close on the draft Connectivity and GNA and Distribution Open Access Regulations 2026
Maharashtra
31 October
TNERC comments close on nine draft regulations
Tamil Nadu
2 November
YEIDA Sector 28 400 kV transmission bids due
Uttar Pradesh
4 November
Bids due on the TGREDCO solar with storage, wind and round-the-clock renewable tenders
Telangana

AISIGINT tracks grid, regulation, land and operator moves across Indian datacenter markets, and uses that evidence in site-level power and delivery assessments. This note is general market information, not advice on a specific site or transaction. Corrections and additions are welcome at info@aisigint.com.

Get the next issue

One email a week on Indian datacenter markets.

Grid, power cost, policy and new capacity, with facts and judgement kept apart.

All past issues →

Free. One email a week. We send a confirmation link first, and every issue has an unsubscribe link. See the privacy policy.