Datacenter campuses on a state grid can now add a direct national grid connection of 50 MW or more
Andhra Pradesh signs MoUs for a 1.8 GW AirTrunk plan and a 2 GW AI compute park, lifting its unbuilt datacenter pipeline to 9,498 MW. Tamil Nadu is told to tender 3,000 MW of medium-term power, and Noida takes a first step on a 765 kV upgrade.
National grid access for state-connected campuses
The national power regulator, CERC, made the Fourth Amendment to its connectivity and General Network Access (GNA) rules final in Regulation No. 209, dated 11 November. It comes into force on publication in the Gazette.
New Regulation 17.5 lets an entity drawing power from a state transmission or distribution network connect directly to the interstate transmission system for part of its existing drawal capacity, not less than 50 MW, or for all of it. It needs the consent of the state transmission utility and the discom, which may process the request in a time-bound manner. The entity keeps paying cross subsidy surcharge, additional surcharge, wheeling, standby and other charges on both connections.
- Regulation 23A: GNA for an identified load moves to a buyer of that load, once the GNA is effective.
- A one-time GNA charge of ₹1 lakh per MW is due within 15 days of the GNA effective date. If unpaid, connectivity bank guarantees are encashed or grid transactions are barred.
- Application fee: ₹5 lakh at 50 MW and above, ₹1 lakh below.
- Connectivity may be withdrawn in full where the final grant is delayed two years or more.
Andhra Pradesh
Andhra Pradesh has 9,498 MW of datacenter projects not yet operating across 15 projects, up from 7,698 MW and 13 projects last week. None has a named connection substation.
AirTrunk signed an MoU for two datacenter campuses with a combined 1.8 GW in Anakapalli district at the CII Partnership Summit in Visakhapatnam: Rambilli at 400 MW and Tootipala at 1,400 MW of IT load. Deccan Chronicle reports an investment of ₹1,03,018 crore and 3,120 jobs. Stage: MoU. No land allotment, government order, investment board clearance or environmental filing has been found.
CleanMax and Neysa plan a 2 GW AI compute park on about 600 acres in the Orvakal zone of Kurnool district, with Neysa anchoring 1 GW of IT load and commissioning targeted for March 2028. CleanMax signed an MoU for a clean energy complex of nearly ₹50,000 crore to power it: 3 GW of wind and solar and 1 GW of pumped storage over five years. Business Today reports that a CleanMax company will apply to the state regulator, APERC, for a licence to supply electricity within the facility.
Day two of the summit listed a Panchshil Realty hyperscale datacenter MoU at ₹37,000 crore. The summit closed with 109 agreements worth ₹9,02,484 crore.
The state transmission roadmap proposes a 400/220 kV Rambilli cluster substation. No tender for it has been found.
Tamil Nadu
Tamil Nadu has 894 MW of datacenter projects not yet operating across 15 projects. None has a named connection substation.
The Tamil Nadu regulator, TNERC, directed the distribution company, TNPDCL, to proceed with tendering for 3,000 MW of round the clock medium-term power from 1 February 2027 to 31 January 2032. This is a direction to tender, not tariff approval. The next hearing is 17 November.
TNPDCL also floated a fifth short-term tender for round the clock power from 18 January to 15 June 2027, peaking at 3,500 MW in March and April. Gas plants are barred after bids of ₹37 to ₹41.50 per unit in earlier tenders.
All three additional surcharge orders remain reserved, and there is still no FY 2026-27 retail tariff order, 138 days after 1 July. Comments on nine draft regulations closed on 16 November.
Uttar Pradesh
Uttar Pradesh has 961 MW of datacenter projects not yet operating across 14 projects; 150 MW has a named connection substation.
The Uttar Pradesh transmission company, UPPTCL, is procuring a design survey for the 765 kV upgrade of the 400 kV GIS substation at Sector-148 Noida. The work is worth ₹1.18 lakh; a 13 November corrigendum moves submission to 20 November. It is the first execution step seen on the 2 x 1,500 MVA, ₹800 crore upgrade in the state rolling plan, the node that sets 2028 to 2031 headroom for the Noida Expressway datacenter cluster.
STT GDC India inaugurated a 22 MW datacenter in Noida, part of about 200 MW it plans across Delhi NCR.
Karnataka
Karnataka has 680 MW of datacenter projects not yet operating across 12 projects. None has a named connection substation.
The state Additional Chief Secretary for Energy put current datacenter demand at 400-600 MW, with about 1,000 MW more in four to five years: about 500 MW in Bengaluru, 200 MW in Mysuru and 200 MW in Mangaluru.
The Karnataka transmission company, KPTCL, re-listed the ₹23.77 crore EPIP GIS (Whitefield) and Puttenahalli transformer package with a 3 December close. It adds 66/11 kV capacity only. The government order for the Karnataka Sustainable Data Centre Policy 2026-2031 and the regulator's GNA regulations are still not notified.
Telangana
Telangana has 8,755 MW of datacenter projects not yet operating across 24 projects, up from 6,607 MW and 18 projects; 612 MW has a named connection substation.
No successor to the ICT Policy 2021-26 has been notified or published in draft, 45 days before the datacenter incentive framework expires on 31 December. The Invest Telangana Global Summit runs 7 to 9 December at Bharat Future City.
Other markets
- Gujarat: the regulator, GERC, adopted a ₹2.34 per kWh tariff for 1,250 MW of solar under GUVNL Phase XXVIII, without storage. It feeds the discom power purchase cost passed through to large power consumers.
- Maharashtra: the regulator, MERC, opened comment on the transmission licence for the 765/400/220 kV Kandalgaon pooling station in Raigad, at levelised charges of ₹326.189 crore a year and completion 24 months from the effective date. It is built to evacuate pumped storage, not to serve load.
- Odisha: draft renewable purchase rules make open access consumers buying conventional power obligated entities, at 35.95% in FY 2026-27 rising to 43.33% in FY 2029-30, plus a storage obligation of 2.5% rising to 4.0%. Comments are due 5 December.
Slip watch
| Asset | State | Was due | Now | Slip |
|---|---|---|---|---|
| Raebareli 400 kV substation | Uttar Pradesh | 30 September 2026 | 31 December 2027 | 15 months |
| Jewar 400/220 kV substation | Uttar Pradesh | September 2025 | Extension sought; hearing 17 November | Over 12 months |
| Sagapara 220 kV STATCOM tender | Gujarat | Close on 7 September | Close on 17 November | 71 days |
| Tharad 220 kV STATCOM tender | Gujarat | Close on 17 September | Close on 18 November | 62 days |
| Dholera-II 400 kV GIS tender | Gujarat | Close on 21 August | Closed 14 October; no award | 54 days |
| Godadara 220 kV GIS tender | Gujarat | Close on 8 September | Closed 14 October; no award | 36 days |
- State
- Uttar Pradesh
- Was due
- 30 September 2026
- Now
- 31 December 2027
- Slip
- 15 months
- State
- Uttar Pradesh
- Was due
- September 2025
- Now
- Extension sought; hearing 17 November
- Slip
- Over 12 months
- State
- Gujarat
- Was due
- Close on 7 September
- Now
- Close on 17 November
- Slip
- 71 days
- State
- Gujarat
- Was due
- Close on 17 September
- Now
- Close on 18 November
- Slip
- 62 days
- State
- Gujarat
- Was due
- Close on 21 August
- Now
- Closed 14 October; no award
- Slip
- 54 days
- State
- Gujarat
- Was due
- Close on 8 September
- Now
- Closed 14 October; no award
- Slip
- 36 days
The Dumas 220/66 kV GIS tender in Surat still closes on 21 November, with no further extension. Dholera-II has no published award 33 days after bids closed.
Capacity and grid
| State | Not yet operating | Connection substation named | Projects |
|---|---|---|---|
| Maharashtra | 11,246 MW | 2,500 MW | 35 (11 no MW) |
| Andhra Pradesh | 9,498 MW | 0 MW | 15 (2 no MW) |
| Telangana | 8,755 MW | 612 MW | 24 (6 no MW) |
| Madhya Pradesh | 1,942 MW | 0 MW | 10 (4 no MW) |
| Odisha | 1,175 MW | 0 MW | 10 (6 no MW) |
| Uttar Pradesh | 961 MW | 150 MW | 14 (5 no MW) |
| Tamil Nadu | 894 MW | 0 MW | 15 (8 no MW) |
| Karnataka | 680 MW | 0 MW | 12 (7 no MW) |
| Gujarat | 588 MW | 0 MW | 7 (3 no MW) |
| West Bengal | 295 MW | 0 MW | 8 (5 no MW) |
| Chhattisgarh | 280 MW | 0 MW | 4 (1 no MW) |
| Haryana | 200 MW | 0 MW | 2 (1 no MW) |
| Bihar | 150 MW | 0 MW | 1 |
| Delhi | 0 MW | 0 MW | 2 (2 no MW) |
| Kerala | 0 MW | 0 MW | 1 (1 no MW) |
| Punjab | 0 MW | 0 MW | 4 (4 no MW) |
| Rajasthan | 0 MW | 0 MW | 2 (2 no MW) |
- Not yet operating
- 11,246 MW
- Connection substation named
- 2,500 MW
- Projects
- 35 (11 no MW)
- Not yet operating
- 9,498 MW
- Connection substation named
- 0 MW
- Projects
- 15 (2 no MW)
- Not yet operating
- 8,755 MW
- Connection substation named
- 612 MW
- Projects
- 24 (6 no MW)
- Not yet operating
- 1,942 MW
- Connection substation named
- 0 MW
- Projects
- 10 (4 no MW)
- Not yet operating
- 1,175 MW
- Connection substation named
- 0 MW
- Projects
- 10 (6 no MW)
- Not yet operating
- 961 MW
- Connection substation named
- 150 MW
- Projects
- 14 (5 no MW)
- Not yet operating
- 894 MW
- Connection substation named
- 0 MW
- Projects
- 15 (8 no MW)
- Not yet operating
- 680 MW
- Connection substation named
- 0 MW
- Projects
- 12 (7 no MW)
- Not yet operating
- 588 MW
- Connection substation named
- 0 MW
- Projects
- 7 (3 no MW)
- Not yet operating
- 295 MW
- Connection substation named
- 0 MW
- Projects
- 8 (5 no MW)
- Not yet operating
- 280 MW
- Connection substation named
- 0 MW
- Projects
- 4 (1 no MW)
- Not yet operating
- 200 MW
- Connection substation named
- 0 MW
- Projects
- 2 (1 no MW)
- Not yet operating
- 150 MW
- Connection substation named
- 0 MW
- Projects
- 1
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 2 (2 no MW)
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 1 (1 no MW)
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 4 (4 no MW)
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 2 (2 no MW)
A substation counts as named only when a utility or regulatory document names it, and naming is not a promise of power. Across these states 36,664 MW is not yet operating, up from 32,716 MW last week; 3,262 MW has a named connection substation, unchanged.
Net read
The week added a national connection route and 3,948 MW of pipeline, but no new named connection substation.
- What looks solid: the final CERC GNA Fourth Amendment of 11 November, and the TNERC direction to tender 3,000 MW from 1 February 2027.
- What to discount: Andhra Pradesh summit MW until land is allotted and a transmission tender is issued, and the Sector-148 765 kV upgrade until works are awarded.
Dates ahead
- 17 November
- TNERC hearing on the TNPDCL 3,000 MW medium-term tender
- Tamil Nadu
- 17 November
- Hearing on the Jewar 400/220 kV substation extension
- Uttar Pradesh
- 23 November
- Bids due on 1,250 MW / 5,000 MWh battery storage
- Andhra Pradesh
AISIGINT tracks grid, regulation, land and operator moves across Indian datacenter markets, and uses that evidence in site-level power and delivery assessments. This note is general market information, not advice on a specific site or transaction. Corrections and additions are welcome at info@aisigint.com.