Navi Mumbai datacenters need 4,000-5,000 MW of grid connection against 1,500-2,000 MW sanctioned
Telangana sets a ₹0.82 per kWh open access surcharge to March 2027, up from ₹0.13. Bids for the 400 kV substation serving the Sector 28 datacenter cluster near Jewar move to 17 November. AdaniConneX agrees to buy the company that holds the Vizag Mega datacenter park for ₹1,085.51 crore.
Maharashtra: 11,246 MW in the pipeline, a Navi Mumbai connection gap
11,246 MW of datacenter projects in Maharashtra are not yet operating, across 34 projects (10 publish no MW), up from 11,066 MW and 32 projects last week. 2,500 MW has a named connection substation.
State Energy Department figures reported by Business India put the connectivity need of about 15 Navi Mumbai datacenters at 4,000-5,000 MW, against 1,500-2,000 MW sanctioned. The gap is about 2,500-3,000 MW. 25 acres have been sought from the state industrial development corporation, MIDC, for a new 765 kV substation and associated works, to be built through a special purpose vehicle. The request has gone unanswered for about 18 months; a fifth letter was sent in mid-October. The Additional Chief Secretary (Energy) says a 765 kV substation takes three to five years. The substation is not named. We set out what this shortage means for the Mumbai region to 2030 in our latest blog.
The Maharashtra regulator, MERC, has issued no hearing notice or final text for its draft network access and open access regulations. No award was found for the Kalwa and Padghe, Hinjewadi, Balewadi or Kharadi substation works.
Telangana: 6,607 MW, open access surcharge up to ₹0.82 per kWh
6,607 MW of datacenter projects in Telangana are not yet operating, across 18 projects (5 publish no MW). 612 MW has a named connection substation.
The Telangana regulator, TGERC, set the additional surcharge at ₹0.82 per kWh for open access consumers buying from sources other than the distribution companies (discoms), from 1 November 2026 to 31 March 2027. The April to September 2026 rate was ₹0.13 per kWh. October 2026 is not recoverable because the discoms filed late. The order number and date are not in press coverage, and the order is not yet on the TGERC orders page.
The reported basis is 282.56 MW of stranded capacity attributed to open access, out of 11,431.77 MW of long-term capacity, and ₹77.07 crore of net stranded fixed charges over 936.26 million units of open access sales.
TGERC also posted an order on passing on the FY 2022-23 and FY 2023-24 true-ups, in continuation of its 30 March order. It bears on the ₹5,420.23 crore recovery from non-agricultural consumers that began with November bills. Whether it changes the per-unit rate or the large power consumer share is not yet known.
No successor to the ICT Policy 2021-26 has been notified or published in draft as of 9 November. The datacenter incentive framework expires on 31 December, 52 days away.
Uttar Pradesh: 961 MW, Sector 28 substation bids move to 17 November
961 MW of datacenter projects in Uttar Pradesh are not yet operating, across 14 projects (5 publish no MW), up from 951 MW and 13 projects. 150 MW has a named connection substation.
The bid deadline for the 400/220 kV, 3 x 500 MVA GIS substation at Sector 28 of the Yamuna Expressway authority area (YEIDA), the 400 kV source for the Sector 28 datacenter cluster, moved from 2 November to 17 November. The e-reverse auction is now 27 November, the letter of intent 7 December and transfer of the project company 17 December, previously 20 November and 30 November.
Nxtra, the Airtel datacenter business, received a letter of intent from the state industrial development authority, UPSIDA, for a 10 MW datacenter at Saraswati Hi-Tech City, Prayagraj. Reported investment is about ₹220 crore.
Tamil Nadu: 894 MW, all three surcharge orders pending
894 MW of datacenter projects in Tamil Nadu are not yet operating, across 15 projects (8 publish no MW), up from 13 projects. None has a named connection substation.
The Tamil Nadu regulator, TNERC, reserved orders on 5 November on both remaining additional surcharge petitions of the state discom, TNPDCL: ₹0.63 per kWh sought for October 2026 to March 2027, and ₹1.14 per kWh for October 2025 to March 2026. With the April to September 2026 order reserved on 29 October, no rate has been set for any of the three half-years.
TNPDCL doubled its medium-term power request to 3,000 MW round the clock for 1 February 2027 to 31 January 2032. TNERC directed it to file its Resource Adequacy Plan and procurement arrangements; the next hearing is 12 November.
The state electronics corporation, ELCOT, and IITM Pravartak were reported on 5 November to have signed an MoU for a project monitoring unit for a state AI datacenter. No MW, cost, site or timeline is published.
Karnataka: 680 MW, transformer additions for east Bengaluru
680 MW of datacenter projects in Karnataka are not yet operating, across 12 projects (7 publish no MW). None has a named connection substation.
The Karnataka transmission utility, KPTCL, tendered a ₹53.77 crore package for 31.5 MVA 66/11 kV transformer additions at the 220/66/11 kV ITI GIS, Hoody and Brindavan GIS stations, closing 18 November. ITI GIS and Hoody feed the Whitefield, Hoodi and KR Puram datacenter cluster.
A ₹23.77 crore package adds a 31.5 MVA 66/11 kV transformer at EPIP GIS, which serves the Whitefield EPIP datacenter area, closing 19 November. The 400 kV transformer works that closed on 6 November show no award. The Karnataka regulator, KERC, has not notified its network access regulations, 39 days after the proposed date.
Gujarat: 588 MW, open access filings reopen on paper
588 MW of datacenter projects in Gujarat are not yet operating, across 7 projects (3 publish no MW). None has a named connection substation.
The Gujarat transmission utility, GETCO, now accepts medium-term open access applications offline, by physical submission at its office, for the current month, because its online portal is still down. The 400 kV Dholera-II substation tender closed on 14 October; 26 days later no award is published.
The Gujarat regulator, GERC, notified its Grid Interactive Distributed Renewable Energy Regulations, 2026, Notification No. 11 of 2026. Net metering and net billing are capped at 1,000 kW AC. Non-residential energy adjustment is capped at 30% of imported energy per billing cycle, and the excess lapses.
Other markets
- Andhra Pradesh: 7,698 MW not yet operating across 13 projects, none with a named substation. AdaniConneX agreed on 5 November to buy the company that holds the Vizag Mega datacenter park from a group company for ₹1,085.51 crore; MW is not disclosed. The central sanction for the state's Green Energy Corridor-III, 7,872 circuit km and 9,500 MVA, names no Visakhapatnam datacenter node.
- Haryana: the air quality commission, CAQM, invoked GRAP Stage II across NCR on 2 November. Diesel generator restrictions in force since Stage I now sit inside Stage II for NCR datacenter sites. The exemption list is not published.
- West Bengal: the Investment Promotion Policy, 2026 was unveiled on 5 November, with electricity tariff exemption for up to five years. No datacenter-specific terms are reported and no official notification has been found.
- Telangana: bids on the 5,800 MW renewable package for the state discoms now close on 19 November, moved from 4 November.
- Tamil Nadu: the Battery Energy Storage Systems Policy, 2026, reported last week, was formally launched on 3 November. New solar, solar hybrid and wind projects of 1 MW and above must add four-hour storage of at least 10% of capacity. The Government Order number is still not published.
- National: the C-DAC AI compute tender now closes on 13 November, moved from 29 October.
Slip watch
| Asset | State | Was due | Now | Slip |
|---|---|---|---|---|
| Raebareli 400 kV substation | Uttar Pradesh | 30 September 2026 | 31 December 2027 | 15 months |
| Jewar 400/220 kV substation | Uttar Pradesh | September 2025 | Extension sought; hearing 17 November | Over 12 months |
| Sagapara 220 kV STATCOM tender | Gujarat | Close 7 September | Close 17 November | 71 days |
| Tharad 220 kV STATCOM tender | Gujarat | Close 17 September | Close 18 November | 62 days |
| Dholera-II 400 kV GIS substation tender | Gujarat | Close 21 August | Closed 14 October; no award published | 54 days |
| Godadara 220 kV GIS substation tender | Gujarat | Close 8 September | Closed 14 October; no award published | 36 days |
- State
- Uttar Pradesh
- Was due
- 30 September 2026
- Now
- 31 December 2027
- Slip
- 15 months
- State
- Uttar Pradesh
- Was due
- September 2025
- Now
- Extension sought; hearing 17 November
- Slip
- Over 12 months
- State
- Gujarat
- Was due
- Close 7 September
- Slip
- 71 days
- State
- Gujarat
- Was due
- Close 17 September
- Now
- Close 18 November
- Slip
- 62 days
- State
- Gujarat
- Was due
- Close 21 August
- Now
- Closed 14 October; no award published
- Slip
- 54 days
- State
- Gujarat
- Was due
- Close 8 September
- Now
- Closed 14 October; no award published
- Slip
- 36 days
Sagapara moved again, from 2 November to 17 November, and Tharad from 3 November to 18 November. Two new slips sit below the table: the Dumas 220/66 kV GIS substation tender in Surat moved from 2 November to 21 November, and the Sector 28 YEIDA 400/220 kV substation bids from 2 November to 17 November.
Open access cost, October 2026 to March 2027
| State | Additional surcharge | Status |
|---|---|---|
| Telangana | ₹0.82/kWh | Ordered by TGERC |
| Gujarat | ₹0.99/kWh | Ordered by GERC |
| Tamil Nadu | ₹0.63/kWh | Discom petition, not yet ordered |
| Karnataka | ₹0.40/kWh | Interim rate continues |
| Haryana | ₹1.37/kWh | Interim rate continues |
- Additional surcharge
- ₹0.82/kWh
- Status
- Ordered by TGERC
- Additional surcharge
- ₹0.99/kWh
- Status
- Ordered by GERC
- Additional surcharge
- ₹0.63/kWh
- Status
- Discom petition, not yet ordered
- Additional surcharge
- ₹0.40/kWh
- Status
- Interim rate continues
- Additional surcharge
- ₹1.37/kWh
- Status
- Interim rate continues
Telangana moved this week. Its rate applies from 1 November 2026; October is not recoverable. TNERC reserved its order on 5 November.
Capacity and grid
| State | Not yet operating | Connection substation named | Projects |
|---|---|---|---|
| Maharashtra | 11,246 MW | 2,500 MW | 34 (10 with no MW published) |
| Andhra Pradesh | 7,698 MW | 0 MW | 13 (2 with no MW published) |
| Telangana | 6,607 MW | 612 MW | 18 (5 with no MW published) |
| Madhya Pradesh | 1,942 MW | 0 MW | 10 (4 with no MW published) |
| Odisha | 1,175 MW | 0 MW | 8 (4 with no MW published) |
| Uttar Pradesh | 961 MW | 150 MW | 14 (5 with no MW published) |
| Tamil Nadu | 894 MW | 0 MW | 15 (8 with no MW published) |
| Karnataka | 680 MW | 0 MW | 12 (7 with no MW published) |
| Gujarat | 588 MW | 0 MW | 7 (3 with no MW published) |
| West Bengal | 295 MW | 0 MW | 8 (5 with no MW published) |
| Chhattisgarh | 280 MW | 0 MW | 4 (1 with no MW published) |
| Haryana | 200 MW | 0 MW | 2 (1 with no MW published) |
| Bihar | 150 MW | 0 MW | 1 |
| Delhi | 0 MW | 0 MW | 2 (2 with no MW published) |
| Kerala | 0 MW | 0 MW | 1 (1 with no MW published) |
| Punjab | 0 MW | 0 MW | 2 (2 with no MW published) |
| Rajasthan | 0 MW | 0 MW | 2 (2 with no MW published) |
- Not yet operating
- 11,246 MW
- Connection substation named
- 2,500 MW
- Projects
- 34 (10 with no MW published)
- Not yet operating
- 7,698 MW
- Connection substation named
- 0 MW
- Projects
- 13 (2 with no MW published)
- Not yet operating
- 6,607 MW
- Connection substation named
- 612 MW
- Projects
- 18 (5 with no MW published)
- Not yet operating
- 1,942 MW
- Connection substation named
- 0 MW
- Projects
- 10 (4 with no MW published)
- Not yet operating
- 1,175 MW
- Connection substation named
- 0 MW
- Projects
- 8 (4 with no MW published)
- Not yet operating
- 961 MW
- Connection substation named
- 150 MW
- Projects
- 14 (5 with no MW published)
- Not yet operating
- 894 MW
- Connection substation named
- 0 MW
- Projects
- 15 (8 with no MW published)
- Not yet operating
- 680 MW
- Connection substation named
- 0 MW
- Projects
- 12 (7 with no MW published)
- Not yet operating
- 588 MW
- Connection substation named
- 0 MW
- Projects
- 7 (3 with no MW published)
- Not yet operating
- 295 MW
- Connection substation named
- 0 MW
- Projects
- 8 (5 with no MW published)
- Not yet operating
- 280 MW
- Connection substation named
- 0 MW
- Projects
- 4 (1 with no MW published)
- Not yet operating
- 200 MW
- Connection substation named
- 0 MW
- Projects
- 2 (1 with no MW published)
- Not yet operating
- 150 MW
- Connection substation named
- 0 MW
- Projects
- 1
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 2 (2 with no MW published)
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 1 (1 with no MW published)
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 2 (2 with no MW published)
- Not yet operating
- 0 MW
- Connection substation named
- 0 MW
- Projects
- 2 (2 with no MW published)
A substation counts as named only when a utility or regulatory document names it. Naming is not a promise of power.
Net read
Of 32,716 MW not yet operating across tracked states, 3,262 MW has a named connection substation, the same named figure as last week.
- What looks solid: TGERC's ₹0.82 per kWh rate to 31 March 2027, the Sector 28 YEIDA substation timetable to 17 December, and the reserved TNERC surcharge orders.
- What to discount: pipeline MW with no named substation, the West Bengal tariff exemption until notified terms show who qualifies, and Gujarat tender dates until awards are published.
Dates ahead
- 12 November
- TNERC hearing on the TNPDCL 3,000 MW medium-term power request.
- Tamil Nadu
- 13 November
- Bids close on the C-DAC AI compute tender.
- National
- 16 November
- Comments due on nine TNERC draft regulations, including transmission tariff and storage.
- Tamil Nadu
- 17 November
- Bids due on the Sector 28 YEIDA 400/220 kV substation.
- Uttar Pradesh
- 18 November
- KPTCL tender closes for transformer additions at ITI GIS, Hoody and Brindavan GIS.
- Karnataka
- 19 November
- Bids close on the 5,800 MW renewable package for the state discoms.
- Telangana
- 7 December
- Letter of intent due on the Sector 28 YEIDA 400/220 kV substation.
- Uttar Pradesh
AISIGINT tracks grid, regulation, land and operator moves across Indian datacenter markets, and uses that evidence in site-level power and delivery assessments. This note is general market information, not advice on a specific site or transaction. Corrections and additions are welcome at info@aisigint.com.